Summary
We will refurbish two floors of your head office while staff stay in the building, working floor by floor over fourteen weeks. Our price is fixed for the scope in your tender pack, and we would act as principal contractor.
Requirements and our response
| Requirement | Our response | Where to find it |
|---|---|---|
| Occupied-building working plan | Floor by floor, noisy work before 8am | Section 4.2 |
| Principal contractor under CDM 2015 | Yes, with a named site manager | Section 5.1 |
| Fixed price for the full scope | Yes | Section 7 |
| Local labour and apprentices | Two apprentices on site throughout | Section 6.3 |
Source Tender pack, section 3
Pricing summary
Source Our priced schedule, section 7
Key dates
| Milestone | Date |
|---|---|
| Contract award | 16 January 2027 |
| Start on site | 1 February 2027 |
| Floor one handed back | 19 March 2027 |
| Practical completion | 7 May 2027 |
Compliance
- Accredited health and safety management system, certificate in appendix B.
- Insurance certificates for employer's and public liability in appendix C.
- Answers to the full prequalification question set in appendix D.